David Carnick posted this on Sep 22, 2015
FLASHING DETAIL FOR BUILD-UP ROOF SYSTEMS
1. Mechanically attach 2 plies of roofing ply sheet embedded in hot asphalt to substrate, ensure the plies extend 18" past underlying portion of drain flange.
2. On under portion of drain flange, embed 1/3" layer, evenly spread roofing mastic compound.
3. Securely fasten drain flange to substrate using appropriate fasteners.
4. For best results, prime drain flange with asphalt primer. Allow ample drying time.
5. Begin B.U.R. system embedding alternate layers of roofing ply sheet in a feathering application down into and over flange. Note: Ensure asphalt is at a temperature range between 430°F 475°F.
6. Secure grate in place, If applicable
7. Complete roof system with specified surfacing as required


FLASHING DETAIL FOR MODIFIED SINGLE-PLY ROOF SYSTEMS
1. Place reversed sheet of modified over drain hole opening on substrate. Ensure that ply sheet extends 18" past underlying portion of drain flange.
Note: Recommend asphalt primer on under portion of drain flange be applied before hand.
2. Place drain on hot modified ply and secure drain flange to roof substrate using appropriate fasteners.
3. For best results, prime top portion of drain flange with asphalt primer. Allow ample drying time.
4. Back burn modified ply sheet, start roof system down into and over flange. 5. Secure grate in place, If applicable
6. Complete modified single-ply system with specified surfacing as required.


FLASHING DETAIL FOR E.P.D.M. OR RUBBER SINGLE-PLY ROOF SYSTEMS
1. Place single-ply sheet over drain hole on substrate. Ensure that ply sheet extends 18" past underlying portion of receiving drain flange.
2. On under portion of drain flange embed 1/3" of water stop cut off.
3. Securely fasten drain flange to substrate, using appropriate fasteners. 4. Embed single-ply sheet in specified adhesive down into and over top portion of flange.
5. Secure grate in place, If applicable
6. Complete single-ply system with specified surfacing as required.